Power Bill Facts

SAIDI and SAIFI: meanings and formulas

Last checked against the EIA pages:

SAIDI measures how long the average customer is without power in a year. SAIFI measures how often the average customer loses power.

A utility reports both figures for its whole system to the U.S. Energy Information Administration (EIA) on Form EIA-861. Both include customers who had no outage.

SAIDI: minutes without power

SAIDI stands for System Average Interruption Duration Index.

The unit of SAIDI is the minute. A SAIDI of 120 means that the average customer had no power for 120 minutes in the year. That is 2 hours.

SAIDI = customer minutes without power in the year ÷ customers of the utility

SAIDI = System Average Interruption Duration Index. It is the minutes of non-momentary electric interruptions, per year, the average customer experienced.

EIA's words. Source: EIA, Electric Power Annual with data for 2024, Table 11.1, notes (October 2025).

SAIFI: number of interruptions

SAIFI stands for System Average Interruption Frequency Index.

SAIFI is a count. A SAIFI of 1.5 means that the average customer had 1.5 interruptions in the year.

SAIFI = customer interruptions in the year ÷ customers of the utility

Count each interruption for each customer. If the same customer loses power twice, that adds two customer interruptions.

SAIFI = System Average Interruption Frequency Index. It is the number of non-momentary electric interruptions, per year, the average customer experienced.

EIA's words. Source: EIA, Electric Power Annual with data for 2024, Table 11.1, notes (October 2025).

Worked example: two outages in one year

In this example, a utility has 1,000 customers. One outage stops the power of 100 customers for 120 minutes. Later, 50 of those customers lose power again for 60 minutes.

  • Customer minutes without power: (100 × 120) + (50 × 60) = 15,000 minutes.
  • Customer interruptions: 100 + 50 = 150. The second outage counts even though it affects the same customers.
  • SAIDI: 15,000 divided by 1,000 customers is 15 minutes per customer for the year.
  • SAIFI: 150 divided by 1,000 customers is 0.15 interruptions per customer for the year.

The figures are averages for all customers. Here, 900 customers had no outage, 50 had 120 minutes without power, and 50 had 180 minutes.

The numerator counts each customer's experience. The denominator counts all 1,000 customers, including those with no outage. FERC explains both calculations.

Very short interruptions are not in the figures

EIA's form instructions say that momentary outages are not in SAIDI and SAIFI. For a utility that uses the IEEE 1366 standard, an interruption counts when it is longer than 5 minutes. A utility with a different method tells EIA its own limit.

Major event days

A large storm can cause more outage minutes in some days than a utility has in a usual year. For this reason, a utility reports each figure two times: with major event days and without them.

For utilities using the IEEE method, a Major Event Day is any day that exceeds a daily SAIDI threshold called Tmed. Tmed is a duration statistic calculated from daily SAIDI values from the past five years. For utilities not using IEEE methods, Major Events are self-determined by the reporting utility.

EIA's words. Source: U.S. Energy Information Administration, Electric Power Annual with data for 2024, Table 11.1, notes (October 2025).

  • The figure with major event days shows all the time without power.
  • The figure without major event days shows the time without power on the other days of the year.

A national example: 2024

EIA publishes US figures in its Electric Power Annual. This example uses the 2024 figures for utilities of all methods.

EIA's US reliability figures for 2024, all methods
FigureWith major eventsWithout major events
SAIDI (minutes per year)611.3126.0
SAIFI (interruptions per year)1.521.04

Source: EIA, Electric Power Annual, Table 11.1. 611.3 minutes is about 10 hours.

This site also computes a median of the utilities with a page. For 2025, 889 utilities have a figure. The median SAIDI was 169.4 minutes with major event days and 100.1 minutes without them.

In a median, each utility counts one time. In EIA's US figure, a utility with more customers has more weight. The site median and the 2024 national example cover different years.

Why the figures of two utilities are not fully equal in meaning

  • The method. EIA lets a utility use the IEEE 1366 standard or a different method. Each utility page names the method.
  • The limit for a short interruption. A utility with a different method sets its own limit in minutes.
  • The record of outages. EIA's file says if a utility has a system that records outages automatically.
  • The supply from the high-voltage system. An outage can start outside the system of the utility. EIA's file has a separate figure without these outages.
  • The count of customers. EIA's file says if a utility includes inactive accounts in its customers.

For these reasons, this site shows each figure as the utility reported it and puts no judgement on it.

What the figures do not show

SAIDI and SAIFI are for the whole system of a utility. They do not show the outages of one street, one town or one county. They do not show how long one outage was.

A state utility commission can have more reports about the utilities that it regulates.

Read a utility's outage figures

Find your electric utility, then open its outage section. Check the year, calculation method and treatment of major event days before comparing two figures.

Adams-Columbia Electric Coop reports both SAIDI figures for 2025, using IEEE methods.

Minutes without power per customer in 2025
BasisMinutes
With major event days107.9
Without major event days66.1

The two figures use the same year and utility. They include different days, so keep the basis beside each value.

These are system averages, not an outage duration for each customer. Download the state utility table to compare the reported fields.